Logo

Ferguson Marine Confirms GLEN ROSA on Track for Q2 2026 Delivery

  • In a letter to the Scottish Parliament’s Net Zero, Energy & Transport Committee, Ferguson Marine CEO Graeme Thomson confirms progress on GLEN ROSA.
  • Key milestones include removal of funnels (20 May), silencer installation (from 24 June), and dry dock scope finalisation with Dales Marine (for 17 July).
  • LNG-related upgrades and galley equipment installation (24 September) are also scheduled.
  • Delivery remains on track for Q2 2026, with a forecast cost of £172.5 million and £12.5 million risk contingency.
  • A site visit for the Committee is planned for 19 September 2025.

Photo: Wikipedia Dave Souza



Source

Related News

Cruise Ship Hantavirus Outbreak Points to Virus Sp...

1 day ago

Three Cruise Ship Passengers Die In Suspected Hant...

3 days ago

The Mediterranean’s Super-Yacht Summer Is Moving W...

4 days ago